Datacenter Cancellations Surge as AI Boom Hits Infrastructure Reality
The artificial intelligence infrastructure buildout is colliding with economic and political reality, as dozens of planned US datacenters face cancellation or delay amid supply chain constraints, energy shortages, and an unexpected obstacle: organized local opposition.
Investment research firm MacroEdge tracked 26 datacenter project cancellations through January 2026—up from a single cancellation in October 2025—according to research shared with climate news outlet Heatmap. The spike in abandoned projects raises questions about whether the US can expand infrastructure fast enough to support the AI boom that has powered economic growth for the past 18 months, MacroEdge chief economist Don Johnson warned.
The wave of cancellations stems from what Johnson describes as a "complex knot of issues." Supply chain bottlenecks continue to plague construction timelines, while regional power grids struggle to provide the massive energy loads required by AI training facilities. Tariff-induced cost pressures have further constrained project economics, making some developments financially unviable at current AI chip and equipment prices.
But the most surprising barrier has been grassroots community resistance. Local opposition has "derailed some plans," according to MacroEdge's analysis, with rural residents organizing against facilities they view as environmentally destructive and economically questionable. In Michigan, residents have rallied against a planned $7 billion Stargate datacenter, reflecting broader concerns about water usage, electricity demand, and whether AI infrastructure delivers promised local benefits.
The cancellation trend also reflects growing investor caution. Some backers have grown "wary of datacenters amid fears of an AI bubble," the research found, suggesting that capital markets are beginning to question whether current AI investment levels are sustainable.
The timing is particularly significant for corporate finance leaders. Datacenter construction has been a major driver of US economic expansion since mid-2024, with hyperscalers and AI companies racing to build capacity for large language model training and inference. If the infrastructure buildout stalls, Johnson noted, it "could have broader economic implications" beyond the tech sector.
The cancellation surge represents a sharp reversal from late 2025, when datacenter announcements were accelerating. The 26-fold increase in project abandonments over just three months suggests the infrastructure constraints are worsening rather than resolving, despite industry promises that supply chains would normalize and energy solutions would materialize.
For CFOs evaluating AI infrastructure investments or partnerships, the datacenter bottleneck introduces new risk factors. Projects that looked viable in planning stages are hitting real-world constraints—regulatory delays, community opposition, and energy availability—that weren't fully priced into initial models. The question is whether this represents a temporary adjustment period or a more fundamental limit on how quickly the US can scale AI infrastructure.
The datacenter slowdown also complicates the narrative around AI-driven productivity gains. If companies can't access sufficient compute capacity because facilities aren't getting built, the promised efficiency improvements remain theoretical rather than operational.